Construction of major pipeline in Istisu nears completion
Infrastructure
- 16 October, 2024
- 10:48
The village of Istisu in Azerbaijan's Kalbajar district is set to witness a major milestone in its reconstruction this month.
The installation of main pipelines in Istisu will be completed by the end of October.
Elvin Mahmudov, the director of ND COMPANY, revealed to Report that the company is currently engaged in various construction and installation projects across the liberated territories. These include the development of a multifunctional residential complex in central Aghdam, construction of houses in Khidirli village, laying of communication lines in Kangarli village, and the installation of main pipelines in Istisu, Kalbajar.
Mahmudov also shared that the work on the Aghdam-Kalbajar main gas pipeline has already been completed.
Latest News
18:03
President Ilham Aliyev approves Agreement on establishment of Joint Commission on cooperation between Azerbaijan and Algeria
Foreign policy17:53
Azerbaijan, Türkiye, Kazakhstan mull promoting Turkic heritage in Slovakia
Foreign policy17:49
Azerbaijan sees 33-fold surge in copper concentrate production
Industry17:42
Value of ICT services in Azerbaijan rises over 8%
ICT17:33
Photo
Graduation ceremony of Underwater Assault Navy Special Force course held
Military17:29
President Ilham Aliyev ratifies Azerbaijan–Moldova agreement on exchange and mutual protection of classified information
Foreign policy17:13
Erdogan: Türkiye was accused of supporting Azerbaijan during 44-day war
Region17:01
Photo
Court hearing on Karen Hovhannisyan's case gets underway in Azerbaijan
Incident16:50