$24M allocated for SHPP reconstruction in Azerbaijan's Karabakh, East Zangazur
Energy
- 04 September, 2024
- 09:18
Add Report.az to preferred Google sources
Stay up to date with the top news!
AzerEnerji OJSC is set to allocate over 40.5 million manats (over $23.8 million) for the reconstruction of three small hydroelectric power plants (SHPPs) and the integration of six additional SHPPs into the energy system in Karabakh and East Zangazur region of Azerbaijan, Report informs, citing Azerbaijan’s Public Procurement web portal.
AzerEnerji has signed a contract with Azconstruction CJSC, the winning bidder of the relevant tender, to carry out the reconstruction and integration work.
The contract, valued at 40,507,432 manats ($23,827,901), will focus on rebuilding the Gozlu Korpu, Sheylanli, and Ashagi Malibayli SHPPs, while integrating six other SHPPs into the energy grid.
Latest News
15:59
Bosnia and Herzegovina looks to strengthen anti-corruption co-op with Azerbaijan
Foreign policy
15:58
Abas Miskarli: Azerbaijani insurers may allocate just 2–3% of portfolios to risky assets
Finance
15:55
Senegal attaches great importance to anti-corruption co-op, OFNAC chairman says
Foreign policy
15:51
Organized crime groups increasingly using AI to conceal assets, Tunisian official says
Foreign policy
15:45
Azerbaijan's European boxing medal tally reaches 25 in 2026
Individual sports
15:43
Limited investment options constrain Azerbaijani insurers, ASA chief says
Finance
15:43
Egmont Institute director: EU-Azerbaijan relations should remain priority – Exclusive
Foreign policy
15:32
Expert calls for legal and tax reforms to develop Islamic finance in Azerbaijan
Finance
15:25
Burkina Faso welcomes holding of OIC anti-corruption bodies' meeting in Baku
Other