Pashinyan: Reconstruction of Yeraskh-Nakhchivan railway to take up to 1.5 years
Infrastructure
- 22 April, 2026
- 14:04
Add Report.az to preferred Google sources
Stay up to date with the top news!
The work under the Trump Route for International Peace and Prosperity (TRIPP) project is scheduled to begin during this year, Armenian Prime Minister Nikol Pashinyan stated while presenting the ruling Civil Contract party's election program, Report informs via Armenpress.
"I am confident that we will start work in 2026. I think the earliest facilities to be commissioned will be the power transmission lines," Pashinyan stated.
He also noted that the reconstruction of the railway sections from Gyumri to Türkiye and from Yeraskh to Nakhchivan (Azerbaijan) will take approximately one to one and a half years.
Latest News
20:06
Photo
Sites of Memory of Western Azerbaijan: Kichik Mazra villagers subjected to massacre, deportation by Armenians
Domestic policy
19:41
IEA members to release more than 400 million barrels from strategic reserves
Other countries
19:22
ASAN service experience may be introduced in Iraq
Foreign policy
19:07
Photo
CIS social protection officials visit DOST Inclusive Development and Creativity Center
Social security
18:51
Lithuanian, Ukrainian firms sign deal on electronic warfare and drone components
Other countries
18:41
Video
Video from 7th CICA Summit posted on Azerbaijani president's social media
Foreign policy
18:26
Azerbaijan, Latvia discuss defense and defense industry cooperation
Foreign policy
18:01
Tokayev: Trans-Caspian Fiber-Optic Cable is project of international significance
Foreign policy
17:54
Photo
Baku hosts 7th CICA Summit, President Ilham Aliyev addresses the event - Updated
Foreign policy