Lachin's Mishni and Alkhasli hydropower plants generate 106.5 million kWh
Energy
- 25 August, 2026
- 15:01
Add Report.az to preferred Google sources
Stay up to date with the top news!
The Mishni small hydropower plant (SHPP), located on the Hochaz River, the largest tributary of the Hakari River in Azerbaijan's Lachin district, has generated 64.3 million kWh of electricity since it began operations through July this year, Report informs, citing Azerbaijan's Ministry of Energy.
The Alkhasli SHPP generated 42.2 million kWh of electricity over the same period. The two facilities were commissioned on August 25, 2023, on the Hochaz River in Lachin.
The Mishni SHPP has an installed capacity of 8.25 MW, while the Alkhasli plant has a capacity of 6 MW.
Combined, the two small hydropower plants have generated 106.5 million kWh of electricity since the start of their operations through July 2026.
Latest News
00:03
US LNG exports rise 21% in January–September 2026
Other countries
23:42
US approves disaster recovery funding across 48 states
Other countries
23:21
US working on local humanitarian ceasefires in Ukraine, first lady says
Other countries
23:08
Photo
Farid Gayibov attends European Games coordination meeting
Individual sports
22:48
Azerbaijan congratulates Türkiye on COP31 organization
Foreign policy
22:32
FIFA confirms hosts for 2031 and 2035 Women's World Cups
Football
21:55
European Commission tightens visa rules for Russian military personnel, tourists
Other countries
21:33
Photo
Alena Aliyeva visits DOST Center for Inclusive Development and Creativity
Domestic policy
21:12
NATO to strengthen air, anti-drone defenses on its eastern flank
Other countries