Aghdam–Khankandi railway construction reaches 44% completion
Infrastructure
- 31 July, 2026
- 15:11
Add Report.az to preferred Google sources
Stay up to date with the top news!
Work continues on the Aghdam–Khankandi railway line, one of the new transport routes in Karabakh, Azerbaijan.
According to Report, citing Azerbaijan Railways (ADY) CJSC, 90% of design work and nearly 44% of construction work have been completed.
The railway line will stretch 30.8 km and include 130 engineering structures: 6 bridges, 5 road underpasses, 2 pedestrian crossings, and 47 reserve crossings.
It was noted that the concept designs of the Asgaran and Khojaly stations have already been finalized, while construction of the Khankandi Railway and Bus Terminal Complex is progressing rapidly.
Latest News
23:05
Photo
Azerbaijani judokas win three gold medals at European U-23 Championships in Italy
Individual sports
21:58
Those turning a TikTok montage into political message: Turkish media urged to act responsibly
Region
21:17
Azerbaijani judoka wins silver at Abu Dhabi Grand Slam
Individual sports
21:14
Armenia-Azerbaijan peace process discussed in Bahrain
Region
20:20
Video
Erdoğan: Türkiye to continue efforts to ensure security in Black Sea
Region
19:14
Azerbaijani wrestler Arsenii Dzhioyev wins world championship silver in Astana – Updated-3
Individual sports
17:54
President Ilham Aliyev's official social media accounts: A reminder to readers
Domestic policy
17:43
Startups act as engine of economic growth, transformation, Azerbaijani deputy minister says
ICT
17:26
Sustainable energy supply vital for startup ecosystem formation, official says
Energy