255 km of TAP lined up in Albania and Greece

255 km of TAP lined up in Albania and Greece Pipes lined up in 1/3 of route
Energy
March 15, 2017 13:25
255 km of TAP lined up in Albania and Greece
TAP

Baku. 15 March. REPORT.AZ/ Pipes lined up in 1/3 of Albania and Greece route of the Trans-Adriatic Pipeline (TAP) project, which will transport Azerbaijani gas to Europe.

Report informs citing TAP, it means 255 km of the pipeline route in the two countries (765 km).

Notably, TAP, which is a part of Southern Gas Corridor project, will initially transport annual 10 bln cubic meters of the gas produced within 'Shah Deniz 2' project, to Europe. This pipeline will join TANAP (Trans Anatolian) pipeline in Kipoi territory on Turkey-Greece border and cross Greece, Albania and the Adriatic Sea before going onshore in southern Italy.

After reviewing various selection options during two years, on June 28, 2013, 'Shah Deniz' Consortium has officially declared selection of the project on TAP project. The pipeline is 878 kilometers long, which 550 km will cover Greece, 215 Albania, 105 Adriatic Sea and 8 km Southern Italy. Highest point of the pipeline will be in the mountains of Albania (1 800 meters), the lower part (-820 meters) beneath the sea.

TAP's groundbreaking ceremony was held in Thessaloniki, Greece on May 17, 2016. Azerbaijani gas will be delivered to Europe on 2020. BP (20%), SOCAR (20%), 'Snam S.p.A.' (20%), 'Fluxys' (19%), 'Enagas' (16%) and 'Axpo' (5%) companies acting as TAP shareholders. 