Head of AzVirt: Our next goals are airports of Zangilan and Lachin
Infrastructure
- 05 September, 2021
- 11:04
Add Report.az to preferred Google sources
Stay up to date with the top news!
Most of the construction work at Fuzuli International Airport has already been completed, Director of AZVIRT construction company Kamil Aliyev told media, Report informs.
He noted that the airport runway length is 3 kilometers, and the width is 60 meters. Construction work at the airport has been underway since January 14.
"We can say that 95% of all work has already been completed. During construction, the territory was also cleared of mines. At the same time, there was no infrastructure for construction work, so we were simultaneously working on its formation. It is a great honor for us to welcome the first test flight. Our next targets are the airports of Zangilan and Lachin," Kamil Aliyev said.
Latest News
14:31
Kazakhstan, Kyrgyzstan plan agreements worth around $100 million
Region
14:20
Azerbaijan hopes Pope Leo XIV will attend opening of new Catholic church in Baku
Religion
14:20
Caspian Sea unites Azerbaijan and Central Asia, presidential aide says
Foreign policy
14:05
Azerbaijan Railways announces resumption of Baku–Balakan–Baku passenger service after track repairs
Infrastructure
13:59
Hikmat Hajiyev: Baku seeks to build sustainable security architecture in South Caucasus
Foreign policy
13:51
11 automated hydrological stations installed in Azerbaijan's liberated lands
Karabakh
13:40
Azerbaijan continues restoration of nature sanctuaries in liberated lands
Karabakh
13:28
Photo
Azerbaijan national team plays its latest match at FIFA U-15 World Cup
Football
13:16
Kobakhidze: Azerbaijan, Georgia keen to expand co-op in various sectors
Foreign policy