Repairs to damaged Estlink 2 power cable between Estonia, Finland start
Other countries
- 28 December, 2024
- 12:21
Add Report.az to preferred Google sources
Stay up to date with the top news!
Repair of the damaged Estlink 2 power cable between Estonia and Finland has begun in the Gulf of Finland, Fingrid energy company representative Kimmo Nepola told Helsingin Sanomat newspaper, Report informs via Interfax.
The cable repair work will continue until the end of July, he said.
Nepola noted that the cable repair is estimated to cost tens of millions of euros, with expenses to be split equally between Fingrid and Estonian transmission system operator Elering.
Latest News
17:29
IATA: Processing single transaction costs airlines more than profit earned per passenger
Infrastructure
17:25
Mukhtar Babayev: Water security is a strategic priority for Azerbaijan
Ecology
17:21
Babayev: Azerbaijani consultants play important role in preparations for COP31
Foreign policy
17:19
COP31: Caspian Sea issues among Azerbaijan's key priorities
Ecology
17:12
Elchin Ibadov: SOCAR Türkiye's assets reach 692 billion liras
Energy
17:10
Photo
Azerbaijan House in Brussels hosts Victory Day event
Foreign policy
16:59
Azerbaijan's transport sector to fully transition to electric traction, alternative fuels by 2060
Infrastructure
16:47
Azerbaijan's cement plants, metallurgical industry to transition to carbon capture technologies
Industry
16:33
Opportunities for mutual investment between Azerbaijan, Ghana to be discussed in Baku
Business