Parviz Shahbazov: Serbia hopes for integration into SGC in 2023
Energy
- 04 February, 2022
- 11:51
Add Report.az to preferred Google sources
Stay up to date with the top news!
Serbia hopes that the commissioning of the Bulgarian-Serbian gas interconnector (IGB) in 2023 would make it possible to integrate into the Southern Gas Corridor (SGC), Azerbaijani Energy Minister Parviz Shahbazov wrote on Twitter.
Construction of a new natural gas interconnector between Serbia and Bulgaria began on February 1 and is scheduled for completion in the fourth quarter of 2023.
The total length of the IGB pipeline is 182 km, of which 151 km will run through Bulgaria and 31 km through Greece. The annual throughput of the gas pipeline is provided in the amount of 3 billion cubic meters, but. if there is demand, the capacity can be expanded to 5 billion cubic meters per year.
Pərviz Şahbazov: "Serbiya 2023-cü ildə SGC-yə inteqrasiyasına ümid edir"
Пярвиз Шахбазов: Сербия надеется на интеграцию в ЮГК в 2023 году
Latest News
00:00
Six years since liberation of Azerbaijan's historic Minjivan settlement
Domestic policy
23:47
24 injured as bus crashes into pedestrian overpass in Ankara
Region
23:38
Iran will not give up enriched uranium — Mohsen Rezaei
Region
22:50
Photo
Sabah lose 2-1 to Borussia Dortmund in Champions League
Football
22:36
Canada, Türkiye set to expand cooperation in four areas
Other countries
21:56
Photo
Sahiba Gafarova: TURKPA has become key platform for parliamentary diplomacy
Milli Majlis
21:49
Farida Jabbarova: Truth about fate of over 4,000 Azerbaijanis must reach world
Karabakh
21:13
S&P Global expects sustainable aviation fuel production to rise through 2028
Energy
20:56
Nargiz Gurbanova highlights key areas of Azerbaijan-Hungary ties
Foreign policy