Parviz Shahbazov: Serbia hopes for integration into SGC in 2023
Energy
- 04 February, 2022
- 11:51
Serbia hopes that the commissioning of the Bulgarian-Serbian gas interconnector (IGB) in 2023 would make it possible to integrate into the Southern Gas Corridor (SGC), Azerbaijani Energy Minister Parviz Shahbazov wrote on Twitter.
Construction of a new natural gas interconnector between Serbia and Bulgaria began on February 1 and is scheduled for completion in the fourth quarter of 2023.
The total length of the IGB pipeline is 182 km, of which 151 km will run through Bulgaria and 31 km through Greece. The annual throughput of the gas pipeline is provided in the amount of 3 billion cubic meters, but. if there is demand, the capacity can be expanded to 5 billion cubic meters per year.
Latest News
00:00
22 years pass since national leader Heydar Aliyev's death
Domestic policy20:57
Georgian foreign minister: Azerbaijan is an important partner for us
Foreign policy20:37
Photo
Leyla Aliyeva attends opening of Bone Marrow Transplant Center at Liv Bona Dea Hospital
Health20:31
President of Azerbaijan congratulates Turkmen counterpart on 30th anniversary of recognition of Turkmenistan's neutrality
Foreign policy20:25
Azerbaijan and Hungary discuss strengthening strategic partnership – UPDATED-2
Foreign policy20:05
Ukraine and Azerbaijan hold meeting of renewed business council
Business19:53
Photo
Azerbaijan, Iran mull opportunities to expand cooperation across several sectors
Business19:05
BTC pipeline oil exports average 501,000 barrels per day in October
Energy18:55
Photo