bp as operator of the Azeri-Chirag-Deepwater Gunashli (ACG) field development project advises that the planned maintenance program (turnaround - TAR) on the Deepwater Gunashli platform, which started on April 25 and was planned for 15 days, has now been fully completed ahead of schedule, Report informs, citing BP-Azerbaijan.
All of the program scope has been delivered safely. The production and export systems of the platform have been restarted. Production is currently being ramped up to its pre-program level.
The program scope included inspections and various projects, including valves changeouts and nucleonic sources replacement, as well as required repair works.
These planned events are a necessary part of the long-term reliability, integrity and production performance and are regularly performed in all bp-operated facilities in the region.