Phillips: Future ACE platform topsides 95% ready

Energy
  • 07 October, 2022
  • 07:33
Phillips: Future ACE platform topsides 95% ready

Topsides of the future Azeri Central-East (ACE) platform, from which oil production will begin in 2023, are 95% ready, Neal Phillips, project general manager for the ACE project, told journalists, Report informs.

He noted that the supporting block of the platform is already fully completed and ready to be sent to the sea to the place of the future installation.

There are plans to use all the possibilities for the project: the already existing ACG infrastructure, that is, existing platforms, underwater pipelines and the Sangachal terminal, Phillips said.