Dispatch of project ACE support block scheduled for 1Q23

Energy
  • 07 October, 2022
  • 08:28
Dispatch of project ACE support block scheduled for 1Q23

BP group has completed more than 80 percent of the Azeri Central-East (ACE) platform construction, Neal Phillips, project general manager for the ACE project, told journalists, Report informs.

He noted that the launch of the support block for the ACE platform is scheduled for the first quarter of next year.

It is expected that the topsides will be sent to sea between April and June. This will depend on the readiness of the barge for this, he added.