BP: Shah Deniz 2 enters start-up phase in run up to achieving first gas in 2018

Baku. 17 May. REPORT.AZ/ After achieving significant construction and commissioning milestones across the whole gas value chain in 2017, the Shah Deniz 2 and South Caucasus Pipeline Expansion (SCPX) projects have now entered the start-up phase in the run up to achieving first gas in 2018.

Report informs referring to the Q1 results of BP-Azerbaijan.

Shah Deniz 2 first gas scope is now 99 percent complete, in terms of engineering, procurement, construction and commissioning.

During the first quarter of 2018, hook-up and commissioning activities continued on the Shah Deniz Bravo platform with strong progress on both topsides. Overall progress is slightly ahead of schedule at over 90% complete. The facility is under operations control and start up procedures are progressing well with final checks under way ahead of introduction of hydrocarbons from the terminal.

The Shah Deniz 2 onshore facilities are now integrated with the operating Sangachal terminal following the removal of the fence that previously segregated them. Hydrocarbons have been introduced into the plant, a significant milestone that is essential for both first commercial deliveries and the subsequent start of production from the Shah Deniz Bravo facilities later this year.

Other News

Price of Azerbaijani oil exceeds $107 07 November, 2026 / 10:08
Azeri Light crude nears $107 per barrel 06 November, 2026 / 10:07
Brent exceeds $100 06 November, 2026 / 09:31
Azeri Light oil price falls to $106 05 November, 2026 / 09:52