The newly-built Khankendi re-floated at Baku Shipyard

The newly-built Khankendi re-floated at Baku Shipyard The Khankendi is planned to perform subsea construction activities on the Shah Deniz field between 2017 and 2027
Energy
May 18, 2016 13:18
The newly-built Khankendi re-floated at Baku Shipyard

Baku. 18 May. REPORT.AZ/ The subsea construction vessel (SCV) “Khankendi” was recently re-floated into the Caspian Sea at the Baku Shipyard quay. The vessel has been specifically designed and built to install the subsea structures of the giant Shah Deniz Stage 2 gas development project, Report was told in the Shah Deniz consortium.

This follows the safe transportation of the vessel’s hull strips from Singapore to Azerbaijan and their successful integration with bow blocks built at the Baku Shipyard on the Caspian. The Khankendi is currently 80% complete and is on track for full completion by April 2017 when Shah Deniz Stage 2 subsea construction activities are planned to commence. Until that time the vessel will be docked at the shipyard quay for completion of the remaining construction and commissioning activities.

Gordon Birrell, BP’s Regional President for Azerbaijan, Georgia and Turkey, says: “The launch of the vessel out of the dry dock at the Baku Shipyardis an important milestone achieved by Shah Deniz Stage 2 project. The Shah Deniz consortium is proud to be involved in the construction of the Khankendi, which, we believe, marks a new era in the shipbuilding history of not only Azerbaijan but also the entire Caspian region. This flagship of the Caspian oil and gas fleet is designed to construct world-class subsea structures for the first time in the Caspian at the water depth of up to 550 metres. We look forward to the full completion and commissioning of the vessel when it will be deployed to the Shah Deniz area to commence subsea installation works for the Stage 2 gas development project”.

The Khankendi is planned to perform subsea construction activities on the Shah Deniz field between 2017 and 2027. The $378 million facility is a unique vessel built under DNV GL’s (Norway and Germany) classification supervision. It is 155 meters in length, 32 meters in width and has a 13 meter main deck. The vessel will be equipped with dynamic positioning to allow working in 2.5 metre significant wave height (Hs), a 900 metric tonne main crane for 600m subsea operation, an 18-man two-bell diving system, two work-class remotely operated vehicles (ROVs), a strengthened moon pool, two engine rooms with 6x4.4MW + 2x3.2MW generators and has a total weight of 17,600 tonnes and a carrying capacity of 5,000 metric tonnes at 6.5 metres draft. 

Latest news

Orphus sistemi