Second part of TANAP to be tested next month
Energy
- 12 March, 2019
- 11:33
TANAP Phase 1 is planned to be tested on April 15, TANAP Director General Saltuk Duzyol told journalists, Report informs citing Turkish media.
Duzyol noted that this part will be ready for gas transportation to Europe on July 1. According to him, as of February 1, the Phase 1 has been completed by 98%.
The Director General also said that 1.250 billion cubic meters of gas were transported via TANAP from June 30, 2018 to February 28, 2019.
According to him, the volume of gas to be transported via TANAP will be 2 bcm by the end of June, 4 bcm by the end of 2019.
TANAP shareholders are SGC (51%), SOCAR Turkey Energy (7%), BOTAS (30%), BP (12%).
Latest News
20:59
EU envoys agree details of 90 billion euro loan for Ukraine
Other countries20:55
Photo
Video
President Ilham Aliyev was presented with Zayed Award for Human Fraternity - UPDATED 2
Foreign policy20:46
Trump, Xi mull 'many important subjects' in a phone call
Other countries20:36
Azerbaijan – Ireland parliamentary working groups mull expanding cooperation
Foreign policy20:32
President Erdogan: All external interventions in Iran pose significant risks
Other20:17
Photo
SOCAR Capital wins international award for green bond issuance
Energy20:04
Gunmen have killed 162 people in west Nigeria attack, says Red Cross official
Other countries19:59
Photo
WUF13 volunteer training phase launches in Azerbaijan
Infrastructure19:49