BP: Works remain on track to support first production from the ACE project in 2023

BP: Works remain on track to support first production from the ACE project in 2023 Despite the challenges and restrictions caused by the pandemic the Azeri Central East (ACE) project remained remarkably resilient during the first quarter of the year along with the other BP-operated activities, Report informs, referring to BP-Azerbaijan.
Energy
April 29, 2021 14:28
BP: Works remain on track to support first production from the ACE project in 2023

Despite the challenges and restrictions caused by the pandemic the Azeri Central East (ACE) project remained remarkably resilient during the first quarter of the year along with the other BP-operated activities, Report informs, referring to BP-Azerbaijan.

The overall project detailed design engineering works were completed by the end of the quarter. The shipment of major equipment packages and bulk materials to Baku continued in support of the fabrication schedule.

Fabrication activities on the topsides and drilling facilities for the ACE platform continued at the fabrication yard in Bibi-Heybat. These included progressing the heavy lift programme with the installation of all the cellar deck panels, the lifting into the position of the first weather deck sections, and several key drilling module lifts. The mechanical package installation progressed, the pipe fabrication, erection, and cable pulling commenced. The mechanical equipment packages inspection and equipment deliveries continued with living quarters and major vessel delivery on the plan. The living quarters modules have been shipped from Sweden and are expected to arrive in Baku in the second quarter of 2021.

At the Heydar Aliyev Baku Deepwater Jackets factory (BDJF) the jacket fabrication continued at multiple work fronts both in the workshops and on the skid-way. Fabrication activities on the subsea structures and spools also continued.

During the quarter, the project progressed the offshore installation works associated with the produced water management on the Central Azeri platform, as well as the preparation for commencing brownfield works on the East Azeri platform in the second quarter of 2021 to allow the ACE platform to draw power from the Azeri field optimising power generation across the assets. At the Sangachal terminal, the design for the onshore control room was completed to allow for the planned modifications to commence in the fourth quarter.

Overall, the engineering, procurement, and fabrication works remain on track to support the first production from the ACE project in 2023.

ACG is the largest oil field block in Azerbaijan. The first production sharing agreement for the development of the field block was signed on September 20, 1994. On September 14, 2017, a new agreement was signed on the joint exploitation of these fields and production sharing. The agreement provides for the development of the fields by the end of 2049.

ACG participating interests are: BP (30.37%), SOCAR (25.0%), MOL (9.57%), INPEX (9.31%), Equinor (7.27%), ExxonMobil (6.79%), TPAO (5.73%), ITOCHU (3.65%), ONGC Videsh Limited (OVL) (2.31%).

AÇG-də BP (30,37 %), SOCAR (25 %), “MOL Group” (9,57 % 16 aprel 2020-ci il tarixindən “Chevron” şirkətini əvəz edib) INPEX (9,31 %), “Equinor” (7,27 %), “ExxonMobil” (6,79 %), TPAO (5,73 %), ITOCHU (3,65 %), “ONGC Videsh Limited” (OVL) (2,31 %) pay sahibidir.

Latest news

Orphus sistemi